Brief Scenario in Recent
Past The
requirement of power for 1996-97 on energy & peaking capacity basis
as per 15th power survey was 23988 Million units and 4445 MW
respectively. As per CEA norms, 19620 Mus & 3004 MW peaking of
energy was expected to be available in Punjab during the year 1996-97
from various sources, but with the optimum operation of own power plants
and arranging power especially during paddy season from neighboring
states and un-allocated power from Central Sector Projects, the Peaking
capacity available was of the order of 3780 MW and energy available was
of the order of 21220 Mus, Thus gap of energy and Peaking capacity was
reduced from 18.2% to 11.5% and from 32.4% to 15.0%
respectively.
Energy as
infrastructural facility has played the most crucial role in hastening
the pace of economic development. With the sole aim of making Punjab a
power surplus State in future, the Government has been making higher
allocations for this sector. During 1996-97 a sum of Rs.210.46 crores
(16.84 percent) has been provided for energy out of the total plan
outlay of Rs.1250 crores. It is hoped that by the year 1996-97, the
installed capacity shall go up by 1.34 percent i.e. from 3510 MW in
1995-96 to 3557 MW in 1996-97. The prospects of total availability of energy also looks bright as it is estimated to mark
an increase of about 6.6 percent from 20063 million kWh in 1995-96 to
21397 million kWh in 1996-97.
Power Supply Position During 9th Five Year
Plan
|
PEAKING
CAPACITY BASIS |
|
Year |
Requirement |
Availability |
Deficit |
Percentage |
|
1997-98 |
4695 |
3390 |
-1305 |
-27.8% |
|
1998-99 |
4952 |
3525 |
-1427 |
-28.5% |
|
1999-2000 |
5228 |
3875 |
-1353 |
-25.0% |
|
2000-2001 |
5515 |
4179 |
-1336 |
-24.2% |
|
2001-2002 |
5814 |
4743 |
-1071 |
-18.4% |
|
ENERGY
BASIS |
|
1997-98 |
25439 |
21813 |
-3626 |
-14.2% |
|
1998-99 |
26937 |
23154 |
-3783 |
-14.0% |
|
1999-2000 |
28551 |
25839 |
-2712 |
-9.5% |
|
2000-2001 |
30233 |
28136 |
-2097 |
-6.9% |
|
2001-2002 |
31997 |
30366 |
-1631 |
-5.1% |
Special Efforts by
PSEB To reduce the gap
between demand and supply, following steps are also being taken by PSEB
Optimum utilization of State’s own Thermal Power Plants.PSEB has planned
installation of shunt capacitors at various Grid Sub-stations in release
of additional MW capacity from existing power plants.Purchase of power
from neighboring states i.e. J&K and H.P during paddy season.Efforts
are being made for getting maximum power out of un-allocated power from
Central Sector Projects especially during paddy season.Encouraging
co-generation of power by various industries of Punjab Like Sugar, Paper
and Textile etc.
Major Plans
1.
PSEB also wishes to
provide 24 hrs. supply on 3 phase basis to all villagers of Punjab and
work is in progress. All 12428 number inhabited villages in Punjab
were electrified by the year 1976. Now, the Transmission &
Distribution network is being improved / strengthen for giving more
reliable supply to al categories of consumers by renovation of old
existing power plants is also being carried out besides adding new
power plants as per Perspective Plan for the next 10
years.
2. The limitations of
financial resources have prohibited the strengthening of Transmission
& Distribution system adequately in past. The Ninth plan program
for power Development would strive to establish its creditability
& begun to gain consumer confidence.
3.The working Group of
Planning Commission approved an outlay of Rs. 3640 crores for power
sector for 1997-2002.
Installed Capacity as on
31.3.97
|
Own
Projects |
|
Hydro |
|
No. |
Name of the
Projects |
Installed Capacity
(MW) |
Share of Punjab
(MW) |
|
1. |
Shanan Pms |
110.00 |
110.00 |
|
2. |
UBDC Stage
I |
45.00 |
45.00 |
|
3. |
UBDC Stage
II |
46.00 |
46.00 |
|
4. |
Anandpur
Sahib |
134.00 |
134.00 |
|
5. |
Mukerian |
207.00 |
207.00 |
|
6. |
Nidampur
Micro |
1.00 |
1.00 |
|
7. |
Daudhar
Micro |
1.50 |
1.50 |
|
8. |
Rohti Micro |
0.80 |
0.80 |
|
9. |
Thuhi Micro |
0.80 |
0.80 |
|
|
TOTAL (A)
HYDRO |
|
546.45 |
|
Thermal |
|
1. |
GNDTP Stage
I&II |
440.00 |
440.00 |
|
2. |
GGSSTP Stage I,II
&III |
1260.00 |
1260.00 |
|
3. |
RSTP
Jalkheri |
10.00 |
10.00 |
|
|
Total
Thermal |
|
1710.00 |
|
|
Total Own
(A+B) |
|
2256.45 |
|
Common Pool
Projects |
|
|
Total Capacity
|
Punjab's
Share
|
|
1.Bhakra Nangal
Complex |
|
a) |
Bhakra Right Bank
PMs |
685.00 |
348.445 |
|
b) |
Bhakra Left Bank
Pms |
540.00 |
274.687 |
|
c) |
Ganguwal
Pms |
77.65 |
39.499 |
|
d) |
Kotla Pms |
77.65 |
39.449 |
|
2. |
Dehar Power
Plant |
990.00 |
475.20 |
|
3. |
Pong Power
Plant |
360.00 |
89.64 |
|
|
Total |
|
1266.97` |
|
III. |
Central Sector
Projects |
1014.125
MW |
|
|
Grand Total
(I+II+III) |
4537.545
MW |
|